Industry

The entire 500kV line circuit 3 is open.

TH (according to Vietnam+) August 27, 2024 21:18

The 226 km long Quang Trach-Quynh Luu 500kV transmission line project, passing through the provinces of Quang Binh, Ha Tinh and Nghe An, is the final component project of the 500kV circuit 3 transmission line project.

Một đoạn của dự án đường dây 500kV mạch 3. (Ảnh: Vũ Quang/TTXVN)
A section of the 500kV line 3 project

This evening, August 27, the National Power Transmission Corporation (EVNNPT), the Central Power Project Management Board (CPMB) coordinated with relevant units to successfully energize the 500kV Line 3, Quang Trach - Quynh Luu, thereby connecting the entire 500kV Line 3 from Quang Trach (Quang Binh) to Pho Noi (Hung Yen).

The 500kV Quang Trach-Quynh Luu transmission line project is 226 km long, passing through the provinces of Quang Binh, Ha Tinh and Nghe An.

The project has 463 column foundation locations; of which 237 are on mountains, passing through many complex terrains with 197 corridor anchorages; 7 anchorages crossing rivers and large lakes, 15 anchorages crossing national highways. The project was implemented from January 18, 2024 and was approved by the Investor Acceptance Council on August 24, 2024 and agreed to energize.

Once completed, the project will help reduce the load and avoid overloading of existing 500kV lines, ensuring the N-1 criteria, especially when the transmission capacity is high from the Central region to the North at a time when hydropower plants in the North have low generation.

The line also helps to increase the stable transmission reserve on the line, combined with the sections of the 500kV Quynh Luu-Thanh Hoa-Nam Dinh I-Pho Noi line as well as the completed circuit 3 lines from Pleiku 2-Doc Soi-Quang Trach, contributing to supplementing capacity from power sources in the South Central region to the load center in the Northern region.

vna_potal_hung_yen_chuan_bi_chu_dao_cho_le_khanh_thanh_du_an_duong_day_500kv_mach_3_7554723.jpg
Hung Yen Provincial Party Secretary Nguyen Huu Nghia (in black shirt) inspects the 500kV Pho Noi Transformer Station, Viet Hung Commune, Van Lam District.

During the implementation process, the Project has always received the attention and direction of the Prime Minister, ministries, branches, and leaders of Vietnam Electricity Group (EVN). Along with that is the support of authorities at all levels where the project passes through, the consensus and joint efforts of the people who have given up land for the project, and participated in supporting the construction of the foundation excavation phase.

According to EVNNPT leaders, in addition to favorable factors, during the implementation process, the Project encountered many difficulties and challenges in mobilizing machinery and construction equipment simultaneously on the entire route; Difficulties in the route terrain with many locations on high hills and mountains, difficult roads to the column foundation locations, especially difficult when it rains, the roads are steep, slippery, and the construction site is not favorable.

Unfavorable weather conditions included many days of rain, storms, thunderstorms, extreme heat, many days with strong winds lasting from 3 to 7 hours, and thunderstorms... so at many times construction had to be stopped to ensure the safety of workers and construction equipment.

The project also encountered difficulties in mobilizing construction forces to erect poles and pull wires due to urgent construction progress, short implementation time, and simultaneous pole erection and wire pulling volume of large projects.

Along with that, the volume of steel columns is very large while the progress requires supplying columns in a short time, EVNNPT together with CPMB and contractors have made efforts to focus on production, implementing specific solutions to speed up production progress.

Implementing the Prime Minister's direction with the spirit of "only discussing work, no retreat", "overcoming the sun, overcoming the rain, not losing to the storm", working "3 shifts, 4 shifts", "eating quickly, sleeping urgently", engineers and workers of the units participating in the Project have worked with the highest spirit and responsibility to bring the Project to the finish line on time.

EVNNPT leaders said: To meet the progress requirements directed by the Prime Minister, in a short period of time, many work items were deployed simultaneously such as construction and installation, pole erection, wire pulling, positioning frame installation, and technical calibration.

Therefore, in addition to the main force of construction contractors, EVN has mobilized forces from EVNNPT and 5 Power Corporations to participate in construction support with a large number of qualified, experienced and skilled human resources.

With the importance of the Project, not only for EVNNPT, EVN's Power units and other units have shown high spirit and responsibility by participating in enthusiastic support, making great efforts, not afraid of difficulties and hardships.

Along with that, EVNNPT also received construction manpower support from the military, Viettel Group, Vietnam National Oil and Gas Group, Vietnam Posts and Telecommunications Group... to participate in supporting pole erection and wire pulling for the Projects.

The completion and energization of the Project meeting the Prime Minister's direction is a great motivation for the entire construction site of the 500kV line 3 project to complete acceptance and inauguration in the coming days according to the Prime Minister's direction to celebrate the 79th anniversary of the August Revolution and National Day September 2.

The completion of the 500kV Quang Trach-Quynh Luu transmission line project is the final component project of the 500kV circuit 3 transmission line project.

Previously, EVNNPT completed energizing the Thanh Hoa 500kV Transformer Station on June 28, 2024, the Nam Dinh 1-Thanh Hoa 500kV Transmission Line Project completed on June 30, 2024, the Quynh Luu-Thanh Hoa 500kV Transmission Line Project and Nam Dinh 1-Pho Noi Thermal Power Plant completed energizing on August 19, 2024.

TH (according to Vietnam+)