This is the target set by the National Power Transmission Corporation for the Gia Loc 220kV Transformer Station and Transmission Line Project (Hai Duong).
Accordingly, this unit strives to complete the Gia Loc 220kV transformer station project before June 30.
By March 21, the construction unit had completed the work such as the road to the transformer station, transformer foundation, equipment pillar foundation, drainage system, emergency oil tank, installation of busbar gate poles, pulling and hanging busbar wires, self-contained transformer station...
For the 220kV line, all 19 poles have been erected, 5/14 anchorages have been pulled, and 3 anchorages are under construction.
The Gia Loc 220kV Transformer Station Project is invested by the National Power Transmission Corporation and built in Gia Phuc Commune (Gia Loc). The 220kV connection line passes through Gia Phuc and Gia Xuyen Communes (Hai Duong City). The project has a scale of 3 220kV transformers, with a total capacity of 750 MVA. In this phase, 2 transformers will be installed, each with a capacity of 250 MVA.
The 220kV line consists of 4 circuits from the Gia Loc 220kV transformer station, connected to 2 circuits of the Hai Duong - Pho Noi 220kV line, with a route length of about 5.37 km.
The completion of the Gia Loc 220 kV transformer station project will significantly contribute to ensuring electricity supply for Hai Duong province and neighboring provinces from this year's hot season. This is an area with rapid economic growth and a huge demand for electricity for production and daily life.
THANH HOA