According to the Hai Duong Province Construction Investment Project Management Board, as of May 10, the contractor in charge of the Road Project to the Con Son - Kiep Bac relic site (section from National Highway 37 to Con Son Pagoda) had completed about 50% of the project volume.
The contractor has basically completed the excavation and embankment of the roadbed, and is currently constructing the sidewalk and paving 2 km of asphalt concrete. Currently, the project is still stuck with the land clearance at the expansion of the 2 intersections with Highway 37.
According to the approved project, the section to Con Son Pagoda consists of 2 main routes, with a total length of nearly 3.7 km, located in Cong Hoa Ward (Chi Linh). Route 1 basically follows Provincial Road 398, which is more than 2.4 km long, while Route 2 is nearly 1.3 km long.
The road surface is 10.5 m wide, with a design speed of 50 km/h. The project has a total investment of 279 billion VND, started construction on December 5, 2023, and is expected to be completed in December 2024...