Hai Duong City People's Committee proposed to remove 27 projects and constructions from the 2025 land use plan.
According to the People's Committee of Hai Duong City, in 2024, the city will have 232 projects and works approved for land use plans with a total area of more than 851 hectares.
The estimated results are that by the end of 2024, 22 projects will be implemented, of which 12 projects have been completed and 10 projects have been partially implemented.
There are 183 projects transferred to the 2025 land use plan, of which 19 projects have basically completed site clearance, 59 projects are continuing site clearance, and 105 projects have not been implemented.
Hai Duong City People's Committee proposed to remove 27 projects and constructions from the 2025 land use plan.
Projects proposed to be cancelled because after 3 years there has been no decision on land recovery; no permission to change land use purpose; no site clearance required; not in accordance with planning; have been merged into other projects...
According to the assessment of Hai Duong City People's Committee, the implementation of the city's land use plan in 2024 has achieved many results but there are still some limitations.
Progress in implementing land use plans is still slow. Many ongoing projects have had to stop, waiting for documents guiding the implementation of the 2024 Land Law...