According to the Management Board of the Project for Comprehensive Development of Dynamic Urban Areas of Hai Duong City, by early June, construction units had completed about 30% of the work volume of 9 construction packages.
Construction of wastewater collection system, connecting households in the west of Hai Duong city
The infrastructure completion package for Nguyen Luong Bang and Thanh Binh streets has completed the drainage system, paving the sidewalks, etc., reaching an estimated 85% of the volume, ensuring progress. The T1 canal embankment package has completed 70% of the work. The construction of Lo Cuong pumping station and new equipment has reached 27% of the plan and is behind schedule. The two packages for the construction of a wastewater collection system, connecting households in the area north of Nguyen Luong Bang street to Thai Binh river and the remaining area west of the city, have reached 29% of the construction value.
Three packages including the construction of the drainage system north of the railway, the Bach Dang river embankment, and the wastewater pumping stations have only completed 2-4% of the work volume. The package for the construction of the wastewater treatment plant and equipment is expected to be awarded on June 30.
PV