Traffic – Urban areas

The Project for Integrated Development of Dynamic Urban Areas of Hai Duong City has achieved about 80% of the workload.

PHAN ANH March 20, 2025 14:00

As of March 18, the Hai Duong City Dynamic Urban Development Project has achieved about 80% of the workload.

goi-thau-8.jpg
The Hai Duong City Dynamic Urban Development Project has completed about 80% of the construction value, of which the construction package of the wastewater collection system and the remaining household connection in the west of the city has reached nearly 90% of the work volume.

According to the Management Board of the Hai Duong City Dynamic Urban Development Project, as of March 18, this project had completed about 80% of the work volume, basically meeting the signed schedule.

ke-song3.jpg
Bach Dang river embankment project has reached about 78% of the workload.

This project has 9 construction packages, the contractor has completed 2 packages HD-PW-01 (completing infrastructure of Nguyen Luong Bang Street and Thanh Binh Street) and HD-PW-02 (T1 canal embankment) and put them into use to effectively prevent flooding in the western area of ​​the city; the remaining 7 construction packages are being implemented simultaneously.

Of the 7 construction packages under construction, package HD-PW-04 (construction of the drainage system north of the railway and equipment) is still facing problems with site clearance and design. This package is at risk of being behind schedule compared to the completion schedule of June 30, 2025.

ke-song-bach-dang.jpg
The Hai Duong City Dynamic Urban Development Project contributes to completing and upgrading the urban technical infrastructure of Hai Duong City. In the photo: Bach Dang River is being solidly embanked.

The Hai Duong City Dynamic Urban Development Project has a total investment of about 1,800 billion VND from World Bank loans and the province's counterpart capital. The project is implemented in 14 wards of Hai Duong City, with the implementation period from 2018 to June 30, 2025.

This project consists of two components: construction and upgrading of urban technical infrastructure; technical support, implementation support. In which, the construction and upgrading of technical infrastructure component will renovate and complete the technical infrastructure system on Nguyen Luong Bang and Thanh Binh streets; renovate the stormwater drainage system to prevent flooding; build a wastewater collection and treatment system for the western area of ​​the city.

PHAN ANH