Hai Duong Provincial People's Council will consider extending the disbursement time of public investment capital for 40 projects in the province with a total amount of nearly 670 billion VND.
On the afternoon of February 28, the Economic - Budget Committee of the Hai Duong Provincial People's Council worked with the Department of Planning and Investment and a number of related units on 4 contents related to public investment. These contents are expected to be submitted by the Provincial People's Committee to the Provincial People's Council for consideration at the 20th Session (the thematic session taking place on the morning of March 1).
Two contents that many delegates are interested in discussing are extending the implementation time and disbursement of capital for the 2023 local budget public investment plan to 2024. Allocating and adjusting the 5-year local budget public investment plan for 2021-2025 and allocating the 2024 capital plan for the second time (capital managed by the province).
According to the plan reported by the Department of Planning and Investment, there are 40 projects that need to extend the implementation time and disbursement of public investment capital from the local budget in 2023 to 2024.
These 40 projects are proposed to extend the disbursement time with a total amount of 669.3 billion VND, mainly projects invested by the provincial level (20 projects with 606 billion VND). Some projects with large total investment include: more than 172 billion VND to invest in building the road to the Con Son - Kiep Bac relic site (1/2 of the left route from An Linh intersection to Dau Rong intersection); more than 93 billion VND to invest in building Hai Duong Obstetrics and Gynecology Hospital phase 2 (inpatient treatment and general services); nearly 87 billion VND to build the extended provincial road 396 (section connecting from provincial road 391 to provincial road 390)...
Members of the Economic - Budget Committee of Hai Duong Provincial People's Council attending the meeting basically agreed with the plan of the Department of Planning and Investment; pointed out some problems in capital structure, project information...
Comrade Nguyen Khac Toan, member of the Provincial Party Committee, Vice Chairman of the Hai Duong Provincial People's Council, requested the Department of Planning and Investment and related units to clarify, review and amend some unreasonable contents related to adjusting the public investment plan. For projects that have met the conditions for capital allocation, Comrade Nguyen Khac Toan requested to follow the correct procedures to allocate public investment early and effectively. Localities and units related to the disbursement of public investment capital need to implement it resolutely and in accordance with regulations.
At the working session, the Economic - Budget Committee of Hai Duong Provincial People's Council also reviewed the submissions and draft resolutions to be submitted to the 20th Session of the Provincial People's Council on deciding and adjusting investment policies for a number of projects.