The Gia Loc 220 kV Transformer Station and connecting line project is being focused on by the construction unit to carry out the first items.
The Gia Loc 220 kV transformer station project and the connecting line in Gia Khanh commune were approved by the National Power Transmission Corporation (Vietnam Electricity Group). The project includes 2 transformers of 250 MVA/unit, a 220 kV line with 4 circuits, nearly 5.3 km long, with a total investment of over 494 billion VND.
The project will be under construction from the end of December 2023 and is expected to be completed in February 2025.
The project, once operational, will meet the electricity needs of Hai Duong as well as some neighboring provinces and cities, contributing to promoting socio-economic development.