Hai Duong Provincial People's Council has issued a Resolution on deciding on the investment policy for the project to build 3 high schools with a total cost of 85 billion VND.

z5390436023818_c36260c7e19e2bd908263f22feea0fce(1).jpg
Kim Thanh High School will be invested in building many new items.

Specifically, Kim Thanh High School will demolish old buildings, including: library, level 4 building, security house and archives. Construct new construction items: 3-storey administrative building, floor area of ​​981 m²; 3-storey subject classroom building with 6 classrooms, floor area of ​​936 m²; 1-storey multi-purpose building, floor area of ​​600 m²; security house 20 m². Construct and renovate technical infrastructure system, fire prevention and fighting system according to regulations.

At Ha Dong High School (Thanh Ha), the old 2-storey administrative building combined with classrooms will be demolished. A new 3-storey administrative building combined with classrooms will be built, with a floor area of ​​1,900 m²; a 1-storey multi-purpose building with a floor area of ​​600 m². Construction and renovation of technical infrastructure and fire prevention and fighting systems will be built.

At Cam Giang II High School, a part of the land area will be leveled, with a leveling scale of about 1,200 m³; 1 outdoor toilet and 1 parking lot will be demolished. A new 3-storey subject classroom building with 15 rooms and a construction floor area of ​​2,629.2 m² will be built. Technical infrastructure, fences and fire prevention and fighting systems will be renovated according to regulations.

The projects belong to Group B, the investor is the Hai Duong Provincial Construction Investment Project Management Board. The total investment of the projects is expected to be 85 billion VND from the provincial budget in the medium-term public investment plan for the period 2021-2025. The project implementation location is on the campus of 3 schools. The project implementation period is 2024-2025.

View resolution detailshere.