THANH HOA June 19, 2024 14:57

The People's Committee of Hai Duong province has just approved the investment policy to implement two 110kV transmission line and transformer station projects, Hung Thai (Ninh Giang) and Nam Sach 2, with a total investment of more than 187 billion VND.

z5550582121024_436cf7dd26bbc24ac8c8fe0a2c2e095c(1).jpg
Two 110kV power line and transformer station projects will help improve electricity quality for localities.

The two projects are invested by the Northern Power Corporation with a total investment of more than 187 billion VND.

The Hung Thai 110kV Transmission Line and Substation Project is being implemented in the communes of Hong Phuc, Tan Phong, An Duc, Hong Duc and Hung Long (Ninh Giang). Accordingly, a double-circuit 110kV transmission line of approximately 8.4 km in length will be built, with a total investment of over VND148 billion. The project is expected to be completed and put into operation in the third quarter of 2025, meeting the demand for load growth in Ninh Giang district and neighboring areas.

The Nam Sach 2 110 kV Transmission Line Project has a total investment of 39 billion VND, located in the communes of Quoc Tuan, An Binh, An Lam, Nam Chinh (Nam Sach). This project is expected to be completed and put into operation in the first quarter of 2025, meeting the demand for load growth in Nam Sach district and An Phat 1 industrial park.