Hai Duong Provincial Construction Investment Project Management Board completes disbursement of public investment capital in 2023

NM February 2, 2024 07:45

According to the Hai Duong Provincial Construction Investment Project Management Board, by the end of January 2024, the unit had completed the disbursement of public investment capital for 2023, ensuring the set requirements.

z5125517756092_91b2e41d6f60a06b185b735b308983f9.jpg
The North-South axis road project of Thanh Mien district, phase 1, is invested by the Hai Duong Province Construction Investment Project Management Board.

In 2023, the Provincial Construction Investment Project Management Board was assigned a public investment capital plan of VND 3,075 billion, including VND 1,287 billion assigned from the beginning of the year, the rest is additional capital. By the end of January 31, the unit had completed the disbursement of the above capital plan. Public investment capital was assigned to the Management Board to implement 46 projects and works. Of which, 43 projects are managed by the provincial budget and 3 projects are managed by the central budget. Transport projects account for nearly 50% of the number of projects and works.

In 2024, the Project Management Board is assigned to implement 27 projects and works in the fields of civil construction, transportation, agriculture and rural development. The total planned capital is 2,472 billion VND.

NM