5 bid packages under the Project for Integrated Development of Dynamic Urban Areas of Hai Duong City ensure construction progress

August 18, 2023 15:03

According to Hai Duong City People's Committee, currently 5 out of 9 bid packages under the Project for Integrated Development of Dynamic Urban Areas are on schedule.


Hai Duong City requires that the road excavation and filling must be carried out to restore the road surface in segments of 40-60 m.

Of which, the completion of infrastructure on Nguyen Luong Bang and Thanh Binh streets reached 96% of the volume; construction of wastewater collection systems and household connections for the remaining areas of the west of the city reached 40%; construction of wastewater collection systems and household connections for the area north of Nguyen Luong Bang Street to Thai Binh River reached 38%; construction of Lo Cuong pumping station reached 30%; construction of wastewater pumping stations reached 20%.

The three packages behind schedule are the T1 canal embankment (80% completed), the construction of the drainage system north of the railway (4%) and the Bach Dang river embankment (5%). The reasons are due to problems in site clearance and complicated construction methods.

The bid package for the construction of a wastewater treatment plant is completing investment preparation steps.