5 bid packages under the Project for Integrated Development of Dynamic Urban Areas of Hai Duong City ensure construction progress
Traffic - Urban - Posted date: 15:03, August 18, 2023
Hai Duong City requires that the road excavation and filling must be carried out to restore the road surface in segments of 40-60 m.
Of which, the completion of infrastructure on Nguyen Luong Bang and Thanh Binh streets reached 96% of the volume; construction of wastewater collection systems and household connections for the remaining areas of the west of the city reached 40%; construction of wastewater collection systems and household connections for the area north of Nguyen Luong Bang Street to Thai Binh River reached 38%; construction of Lo Cuong pumping station reached 30%; construction of wastewater pumping stations reached 20%.
The three packages behind schedule are the T1 canal embankment (80% completed), the construction of the drainage system north of the railway (4%) and the Bach Dang river embankment (5%). The reasons are due to problems in site clearance and complicated construction methods.
The bid package for the construction of a wastewater treatment plant is completing investment preparation steps.