Construction of Gia Loc Industrial Park infrastructure phase 1 reaches 70% of volume
MINH NGUYEN•January 7, 2025 06:32
It is expected that by March, the essential infrastructure items of Gia Loc Industrial Park will be completed, ready to welcome secondary investors.
By early January, the construction of the infrastructure of phase 1 of Gia Loc Industrial Park had reached 70% of the volume. The wastewater treatment plant of phase 1 of the industrial park alone has been basically completed. After secondary investors lease land, build factories, and put them into operation, all wastewater will be discharged into a common tank for treatment to meet standards before being discharged into the environment. In the photo: Workers pouring formwork for the tank roofAt the construction site, there are about 200 workers, laborers from the local area and other provinces coming to work. In the photo: Workers are paving the sidewalk of the main road leading to the industrial park.The industrial park has 6 main roads, which are now basically completed. Workers are working non-stop on weekends to ensure the progress of the remaining items, striving to complete all items of the park by March. Secondary investors can come to build factories from now on and can operate by June.The main roads of the industrial park are being prepared to be paved with asphalt. The traffic system, lighting and drainage systems... will be completed in March.At the construction site, there are many rollers, excavators, bulldozers... leveling the ground to hand over to secondary investors.Currently, there are 6 units constructing infrastructure in Gia Loc Industrial Park, including Joint Stock Companies: Construction and Trade Investment No. 7; Viet Hoa Construction and Trade; Contechco Construction and Trade Investment; B&G Technology and Trade and Limited Companies including: Truong Thanh Construction and Business Investment; Truong Thanh Construction and Business Investment Joint Venture - Thai Linh Construction and Investment
Gia Loc Industrial Park, invested by Nam Quang Infrastructure Investment and Development Joint Stock Company, has a total area of 198 hectares, of which phase 1 is over 98 hectares. Items such as lighting, internal roads, wastewater treatment plant, telecommunications... of phase 1 are being actively constructed by investors.
The goal of Gia Loc Industrial Park is to attract mechanical engineering, electronic assembly, healthcare, logistics and other clean industries that do not pollute the environment. The investor of the industrial park infrastructure is negotiating with many investors in China, Japan, Korea... before signing the land lease contract.