Gia Loc Industrial Park may attract secondary investors in December

MN October 18, 2024 10:23

Gia Loc Industrial Park investor committed to completing basic infrastructure by December 2024 to ensure conditions to attract secondary investors.

gia-loc.jpg
Gia Loc Industrial Park investors are actively building industrial park infrastructure and attracting investment.

Following the direction of Deputy Secretary of the Provincial Party Committee, Chairman of the Hai Duong Provincial People's Committee Le Ngoc Chau in early October, Nam Quang Infrastructure Investment and Development Joint Stock Company (the investor of Gia Loc Industrial Park infrastructure) is focusing on promoting infrastructure construction and promoting domestic and foreign investment.

The industrial park investor has approached potential customers from Japan, Korea, China, etc. Currently, many foreign enterprises have come to survey investment.

To date, the investor has completed the Gia Loc Industrial Park intersection with the North-South provincial road and leveled more than 40 hectares. To speed up the progress, the company has added 2 more contractors to construct technical infrastructure and increased the construction teams.

From October 2024, the industrial park will start construction of a 35 kV medium voltage power supply project. It is expected that this power supply project and a wastewater treatment plant with a capacity of 2,000 m3 will be completed in December.3/day, night.

The investor has worked with Viettel and VNPT to cooperate and invest in developing 5G technology and providing telecommunications services in Gia Loc Industrial Park, ensuring exclusivity and attracting investment.

Gia Loc Industrial Park infrastructure construction and business investment project has a scale of 198 hectares, located in Hong Hung, Toan Thang, Hoang Dieu communes and Gia Loc town, with a total investment capital of 2,062.5 billion VND.

The investor will implement the project in 2 phases. Phase 1 with 98.1 hectares, the investor commits to complete the basic infrastructure by December 2024 to ensure conditions for attracting investment in 45 hectares. By March 2025, the technical infrastructure will be basically completed, attracting investment in the remaining area. Phase 2 is expected to be technically completed in February 2026 on the remaining approved area.