On January 2, the construction site of the bridge over the Sat River and the road leading to the expanded Phuc Dien industrial park on provincial road 394B (Binh Giang) was bustling with labor and production.
The bridge over the Sat River and the approach road to the expanded Phuc Dien Industrial Park has a total length of 430 m, of which the bridge is 130 m long, with a concrete and prestressed reinforced concrete structure, consisting of 2 elements, each element is 12 m wide; the approach road is 300 m long.
The project started on September 2, 2021, and has so far completed nearly 80% of the construction and installation volume. It is expected to be completed by the end of June 2023, connecting National Highway 5, Phuc Dien Industrial Park (Cam Giang) with the expanded Phuc Dien Industrial Park, and Provincial Road 394B.
About 50 officers, engineers, and workers of the joint venture of contractors: Hai Duong Irrigation Construction Joint Stock Company, Investment and Construction No. 18 (LICOGI 18) and the consulting and supervising unit is Construction and Trade Joint Stock Company 628, Construction Design Consulting Joint Stock Company Thang Long implemented.
Units are concentrating on construction machinery to ensure progress and quality of the project.
Preparing for bridge girder construction
Bridge deck construction
The bridge project across the Sat River and the road leading to the expanded Phuc Dien Industrial Park has a total investment capital of nearly 140 billion VND sponsored by Trung Quy Investment Joint Stock Company (Bac Ninh).