On the morning of April 5, the People's Council of Cam Giang district (Hai Duong), term XX, held the 12th session (special session) to approve many important contents, including the addition of a project to expand 2 roads in the district.
At the meeting, Cam Giang district agreed to supplement the Medium-term Public Investment Plan for the period 2021 - 2025 and the Public Investment Plan for 2024 for 3 projects. Notably, the project to renovate and expand Cam Phuc - Luong Dien district road and the project to expand District Road 19 (section from Hai Duong city border to Cam Giang town).
The project to renovate and expand the Cam Phuc - Luong Dien district road has a length of 330 m, with an estimated investment of 10 billion VND from the district budget and other legal capital sources. The project implementation period is from 2024 - 2025.
District Road 19 Project (section from Hai Duong City to Cam Giang Town) has a scale of Grade III road, total investment of 693 billion VND from district budget 50% and proposed provincial budget support 50%. Project implementation period is in the period of 2024-2027.
The third newly added project is the expansion and construction of the perimeter wall of Tue Tinh High School with a total investment of 2.7 billion VND from the district budget and other legal sources.