Provincial Party Secretary Tran Duc Thang attended the inauguration of the 500kV line 3 circuit projects.

THANH HOA-THANH CHUNG August 29, 2024 12:40

On the morning of August 29, in Hung Yen, Vietnam Electricity Group held the inauguration ceremony of the 500kV line 3 circuit project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) in a combination of live and online formats. Hai Duong Provincial Party Secretary Tran Duc Thang attended at the bridge point in Binh Giang.

thu-tuong-29824a(2).jpg
Prime Minister Pham Minh Chinh speaks at the inauguration ceremony of the 500kV line 3 projects. Photo: VNA

The main bridge point is at the 500 kV Pho Noi transformer station (Hung Yen) and 8 bridges in 8 provinces where the project passes through: Hai Duong, Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh. Prime Minister Pham Minh Chinh attended and spoke at the main bridge point of Pho Noi (Hung Yen).

Attending the Hung Yen bridge were comrade Do Van Chien, Politburo member, Chairman of the Central Committee of the Vietnam Fatherland Front, representatives of leaders of central ministries and branches, Vietnam Electricity Group, National Power Transmission Company and Hung Yen province.

Deputy Prime Ministers: Tran Hong Ha, Ho Duc Phoc, Le Thanh Long attended at the bridge points of Thai Binh, Ha Tinh and Thanh Hoa.

cat bang KT duong day)
Provincial leaders, contractors and construction units cut the ribbon at the Hai Duong bridge point.

The Hai Duong bridge was implemented in Binh Giang district. Attending were comrades: Tran Duc Thang, member of the Party Central Committee, Secretary of the Provincial Party Committee; Luu Van Ban, member of the Provincial Party Standing Committee, Acting Chairman of the Provincial People's Committee. Also attending were comrades in the Provincial Party Standing Committee; representatives of departments, branches and sectors; Hai Duong Electricity One Member Co., Ltd., experts, engineers, workers and local people...

f1ddf826-4264-4803-b7e3-05f3d1b44f28-053eddbcb5f8095c565a89c1c8bb3814(1).jpeg
Delegates attending at Hai Duong bridge point

The Quang Trach - Pho Noi 500kV 3rd Circuit Transmission Line Project is a 500kV double-circuit line, approximately 519 km long, passing through 9 provinces, with a total investment of more than 22,300 billion VND, with 4 component projects, starting construction in January 2024. The entire project has 1,177 column foundation locations and 513 anchorage spaces.

The project construction process encountered many difficulties due to the large amount of work, equipment, and techniques, some materials had to be imported, which took time, required a large amount of human resources, and had to be carried out in adverse weather conditions, especially due to intense heat or thunderstorms, and had to be carried out through complex terrain in localities known as “rain bags” or “fire pans”…

To have land to implement the project, about 1.83 million m2 of land was reclaimed and cleared, spanning 9 provinces; support, resettlement, and production stabilization for 167 relocated households and 5,248 affected households.

The 500kV line 3 project from Quang Trach to Pho Noi is of particular importance in improving the transmission capacity of the national power system. The completion of the project will help increase the power transmission capacity from the Central region to the North from 2,200 MW to 5,000 MW to solve the urgent and difficult problem of power supply for the North.

500kv-m3-4685-1724907881.jpg
The 500 kV line 3 circuit put into operation, creating a complete transmission line, stretching from North to South. (Source: Internet)

The power line passing through Hai Duong province is nearly 31km long, including 74 pole foundation locations through Ninh Giang, Gia Loc, Thanh Mien and Binh Giang districts. To serve the project construction, Hai Duong has cleared up to 6.8 hectares of land, affecting 270 households. In December 2023, the province completed the handover of 100% of the pole foot locations and by April 2024, it had completed the handover of 28/28 anchorage spaces to the construction units... During the nearly 8 months of construction, 6 contractors participated in the construction and installation, 4 contractors manufactured and supplied steel poles, 5 contractors supplied ceramic wire accessories, and thousands of workers on the construction site received active support from the provincial government to the grassroots level.

Speaking at the inauguration ceremony, Prime Minister Pham Minh Chinh affirmed that with the direct and drastic direction of the Government, the Ministry of Industry and Trade, the State Capital Management Committee at Enterprises, the effective participation of the entire political system and local authorities at all levels; the consensus, trust, support and encouragement of the people; Vietnam Electricity Group, the National Power Transmission Corporation and contractors have been highly determined, made great efforts, acted decisively, stayed close to the construction site, stayed close to the work with the spirit of "overcoming the sun, overcoming the rain, not losing to the storm", "only discussing work, not discussing retreat", "not enough work during the day, working at night", "eating quickly, sleeping urgently", "working continuously 24/7", "3 shifts, 4 shifts", "working through Tet, through holidays, through holidays". The forces stood shoulder to shoulder, overcoming all challenges, "turning difficult into easy, turning impossible into possible"; Lightning fast construction completed the entire project in more than 6 months, meeting all requirements...

500kv-m3-2-1-l-1724910490-7456-1724910514.jpg
500 kV line 3 passes through 9 provinces, 43 districts, nearly 211 communes

The Prime Minister emphasized that the rapid completion of the work volume doubled or tripled in just one-fifth of the time of the first and second circuit projects demonstrated remarkable maturity, a great achievement, and an outstanding achievement worthy of recognition by the Vietnam Electricity Group, the National Power Transmission Corporation, project management units, contractors, units that supported the construction site, and more than 12,000 engineers, workers, and laborers in the electricity industry who have participated in the project day and night from the start of construction until today.

The Prime Minister commended the Deputy Prime Ministers, ministries, localities, and forces for their determination and efforts to complete the project as directed.

Prime Minister Pham Minh Chinh affirmed that the implementation of the project has shown many valuable lessons that can be applied to many key national projects. These include the leadership, direction, and command, and the strong efforts in performing the tasks; the project has promoted the strength of national solidarity, mobilizing all classes of people to participate in the spirit of sharing together, working together and developing together; the coordination between state-owned enterprises and private enterprises, central enterprises and local enterprises in accordance with the motto "4 on-site"; launching a patriotic emulation movement to motivate forces to participate in the implementation of large and key projects... Units have done a good job of restoring the site, protecting the environment, and operating the power line system safely and effectively; the Party Committee and authorities have paid attention to taking care of the lives of people affected by the project...

THANH HOA-THANH CHUNG